Glassford Bridge Challenge for 80 Tonne Transformer

Loaded with an 80 Tonne transformer, the Collett Team head to South Lanarkshire destined for Harting Rig Wind Farm Substation.


Glassford Bridge Challenge for 80 Tonne Transformer

Appointed by Fracht UK, our Team were tasked with providing a transport solution to deliver the 80 Tonne cargo the 230 miles from Goole to Harting Rig Wind Farm in South Lanarkshire.

A relatively straightforward journey, we left our Goole Heavy Lift facility and slowly made our way to the rural County of South Lanarkshire.  However, a mere three miles from the wind farm site, our Team encountered a challenge, namely Glassford Bridge.

Identified in the planning process, weight restrictions were in place on the structure, resulting in limitations to the vehicles and cargoes crossing the bridge.  The loaded trailer and truck combination would have exceeded the structure’s maximum permitted weights, therefore a new approach would be required.

Delivering Harting Rig Transformer

Alongside the weight limitations, our Team were also required to observe a maximum speed of 10mph and ensure that no other traffic or pedestrians would be present on the bridge during the transport operation.  In addition, all vehicles must stick to a 3m strip of the bridge, with a series of cat’s eye markers in place to ensure each vehicle maintained a set alignment throughout.

With all this identified, our Team executed innovative transport arrangements to overcome these obstacles.  Arriving at Glassford Bridge the process began, first by uncoupling the loaded trailer from the 8x4 MAN TGX tractor unit.  Once disconnected, two 40m wire cables were attached, connecting the trailer and primary ballast truck.  A secondary 8x4 ballast unit was then connected at the rear of the trailer, again using 40m wire cables.

Harting Rig Wind Farm

The extended combination was then ready to go.  Having implemented Temporary Traffic Restriction Orders, the lights on the bridge were turned to red and Collett were able to proceed.  With all other traffic restricted, the secondary ballast tractor reversed and the primary drove forward.  This tensioned the cable, removing any slack, then both vehicles began the slow drive forward.  Controlling the cable tensioning throughout, the primary tractor unit cleared the structure, followed by the trailer, transformer and Steersman in tow.  With the ability to control the trailer steering and braking, Collett’s Steersman ensured that the trailer and cargo remained within the necessary alignment whilst traversing the structure.  Once clear of the bridge, and with the trailer brake applied, the secondary ballast unit took up the cable stack and crossed Glassford Bridge, operation complete!

With the wire cables removed and the primary tractor unit re-coupled, the 80 Tonne transformer completed the remaining 5 miles of the journey to Harting Rig Wind Farm.  On arrival, the cargo was met by Collett’s Heavy Lift Team for jacking & skidding to final position.

More News Stories

Contact Us

Tel. +44 (0)8456 255 233
Email. info@collett.co.uk

Victoria Terminal, Albert Road, Halifax, HX2 0DF
Mistral Point, AW Nielsen Road, Goole, DN14 6UE
Baltic House, Central Dock Road, Grangemouth, FK3 8TY
Naas Industrial Estate, Naas, Co. Kildare, W91 VR8E

DMC Firewall is a Joomla Security extension!

We use cookies to enhance the content of our website and your browsing experience.